Part 1 — General

3 Work not completed

Current to 2025-04-01 · Official PDF

For the purposes of this Act, if
(a) the work under a contract o r a subcontract or a substantial
part of it is ready for use or is being used for the purpose
intended, and
(b) the work under a contract or a subcontract cannot be
completed expeditiously for reasons beyond the control of
the contractor or the subcontractor,
the value of the work to be completed or materials to be furnished
is to be deducted from the contract price in determining substantial
performance.
1985 c14 s3