CPA · Prompt Payment and Construction Lien Act
Part 5 — no later than 21 days after giving the notice to the subcontractor; (c) a copy of any notice of dispute given by the owner under subsection 32.2(2). (6) A contractor who disputes, in whole or in part, the entitlement of a subcontractor to paymen
32.4 PROMPT PAYMENT give notice no later than Notice of non-payment
notice of dispute under section 32.2(2) must, without delay, advise
its subcontractors of the receipt of that notice.
(2) Subject to the regulations, a subcontractor who receives a
notice of non-payment under section 32.3(6) must, without delay,
advise its subcontractors of the receipt of that notice.
2020 c30 s14