MHHS · Prompt Payment and Construction Lien Act
Part 9 — Regulations and Transitional Provisions
72 PROMPT PAYMENT Transitional
deemed to be references to "15%" with respect to the following
contracts or subcontracts under which a builders' lien may arise:
(a) any contract or subcontract e ntered into before September
1, 1997;
(b) any contract solely for the furnishing of materials, the
performance of services or the provision of work by a
labourer entered into before September 1, 1997;
(c) any subcontract entered into on or after September 1,
1997 that is made under a contract entered into before
September 1, 1997;
(d) any contract solely for the furnishing of materials, the
performance of services or the provision of work by a
labourer entered into on or after September 1, 1997 that is
made in respect of a contract entered into before
September 1, 1997.
1997 c24 s1